Phase: Completed
Location: Washington County
Final cost: $39 million
Project Overview
Improvements Complete
The project consisted of the partial reconfiguration of the I-70/I-79 interchange known as the South Junction Interchange. It involved construction of a new fly-over ramp carrying the I-79 northbound to I-70 westbound traffic movement, as well as new concrete roadway on I-79 northbound and the ramp to I-70 eastbound. Work started in September 2011 and was completed in October 2014.
Project Mapping
View project mapping to learn more details about this area.
Contact
Name:
Melissa Maczko
Organization:
PennDOT District 12
Title:
Press Officer
Phone:
724-439-7135
Email:
mmaczko@pa.gov
Construction

Early construction activities for the South Junction Interchange project.